The Village of Ashley project resulted in the Central Ohio Wastewater Services crews in finding significant I/I at the manholes. Crews found 17 manholes next to a creek in the woods that were 16 to 26 ft deep with a very high water table. In looking into the cost for replacement for all the manholes, the cost totaled approximately $300,000.

“The Village of Ashley did a (cured-in-place pipe) CIPP liner project in 2007, removing half the peak flow from 1 million gal/day to 500,000 gal/day at a plant that was designed for 190,000 gal/day,” Howard explains. “We found the infiltration was coming between the CIPP liner and the original pipe releasing at the manholes. The acting engineer at the time had heard of Source One Environmental (S1E) LLC and its product so we gave it a try. Since the start of the project, our average dry time flows have went from 60,000 gal/day to 30,000 gal/day and heavy rain fall events have fallen from 500,000 gal/day to 250,000 gal/day making the plant more efficient.”

Why should you read this? The effectiveness and precise role of chemical grouting is too little understood by sewer network managers, IMNSHO. Trenchless Technology, November 2014